Funded by the German Government through KFW Bankengruppe and in coordination with the Lebanese Ministry of Public Health, the UNDP has implemented several sustainable energy interventions targeting 15 public sector hospitals in response to the impact of COVID-19 in Lebanon. The technologies implemented include PV systems, SWH systems, complete lighting retrofit with LED lamps, VFDs, a Building Management System (BMS) and a computerized maintenance management system (CMMS) to digitize and improve maintenance management at the hospital.
Solar PV
67KWp
Total Capacity
111MWh
Savings per year
30,206$
Savings per year
74tCO2
Savings per year
Solar Water Heaters
5,000L
Total SWH Capacity
196MWh
Savings per year
53,008$
Savings per year
130tCO2
Savings per year
Lighting
4,425Lighting Fixtures
Total Capacity
246MWh
Savings per year
66,788$
Savings per year
163tCO2
Savings per year
Variable Frequency Drives (VFDs)
13
1 Computerized Maintenance Management System (CMMS)